Update from site

Yesterday we had a “lessons learnt” session on site for the phase2 team of to be fully aware of all successes and challenges we (the phase 1 team) had faced since stage E. It was a great chance to have a walk around the site together, and amongst other things, have a look at the site from the south side of the A13. (It really is missing the arrival of plot two if you ask me) After a rather long meeting -luckily for us- minuted by our Project Managers, we had a chance to have a look at the site progress… In the marketing suite we found the model that the client built to (successfully) sell apartments in China The landscaping contractors are working very hard to complete landscaping and you can begin to feel how the podium garden will be once completed. The green wall has already been pluck planted in the north side and bird feeders are already in place The fountain is working And the bench frame is ready to be cladded…